Clients & Projects

2011

JUWI, 5 MW Plant near Jodhpur

SunReign had the opportunity to work with and learn from JUWI who brought 1000MW of EPC experience from around the Globe. SunReign’s scope of work was to execute the DC side mechanical and electrical work.

TATA BP, 1 MW Plant in Barmer

Structure foundations: open trench foundations, inverter room, control room, boundary wall and drainage work.

2012

L&T, 40 MW Plant at Pokran

Commissioned complete DC side work – structure assembly, module mounting and cable terminations till the inverter for one block of 3.2 MW.

L&T, 1 MW Plant at Phagi

End-to-end installation and commissioning – structure foundation, inverter room, control room, transformer foundations, structure assembly, module mounting and cable terminations.

JUWI, 2 MW Plant at Jhansi, UP

Site survey for foundations’ marking, pile drilling, foundation casting, structure assembly, module mounting and cable terminations. The entire job was executed in record 38 days.

JUWI, 2 MW Plant at Rajgarh, MP

DC side mechanical and electrical work in two blocks, totaling 1.3 MW.

2013

JUWI, 20 MW Plant at Bap

12.5 MW of DC Pile Foundation work, 8.5 MW of DC mechanical work and 20 MW of DC Electrical work.

L&T, 17 MW Plant at Bap

Control Room construction and also DC side work of a 3.8 MW block.

JUWI, 20 MW Plant at Ugras

Construction of plant’s Operation & Maintenance Room.

Harsha Abakus, 11 MW Plant at Kolayat

4.7 MW of DC side electrical work.

AEG, 5 MW Plant at Kolayat

Land clearing, leveling and Pile foundations for the module mounting structures.

2014

L&T, 7.5 MW Roof Top Plant in Beas near Amritsar

Civil works: construction of Control Room and two Inverter rooms and the DC side work of 2MW.

L&T 20 MW Plant in Bhadla

Construction of Control Room and the DC side work of 6MW.

L&T 10MW Plant in Cherial, Telengana

Construction of Control room and DC side work of 3.14MW.

2015

JUWI, 50MW Plant in Charanka, Gujarat

Civil works of Inverter and transformer foundations and DC side electrical work of 20MW.

JUWI, 10MW Plant in Shahpura, Rajasthan

Under execution: Civil works of Inverter and transformer foundations and the DC side electrical work of the full 10MW.

Top